Q1 Report 2018

Project Management - Release Process

Release 6.6 & 6.7 News Development is underway for the 6.6 release. We will be deploying 6.6 on November 16, 2017.

Task Name

Duration 80 days 48 days 13.5 days 14.5 days 16.5 days

Start

Finish

Gather Requirements Design & Estimate MS: Release Pause MS: Release Pause Code Development Functional Testing Preliminary Regression

08/31/17 11/09/17 12/04/17 12/05/17 01/02/18 03/16/18 04/13/18 04/27/18 05/04/18 06/21/18 06/15/18 06/21/18 03/16/18 05/17/18 05/21/18 08/30/18 09/28/18 10/15/18 10/22/18 12/07/18 12/12/18 12/13/18

05/09/17 09/01/17 11/13/17 11/13/17 12/06/17 01/03/18 03/19/18 04/16/18 04/30/18 05/07/18 06/18/18 06/21/18 11/13/17 03/19/18 05/18/18 05/22/18 08/31/18 10/01/18 10/16/18 10/23/18 12/10/18 12/13/18

✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓

Estimate Review and Prioritization

50 days 20 days 10 days

UAT

5 days

Release Planning Full Regression

4 days 29 days

MS: Deploy 6.6 to Prod

1 day

Requirements Analysis is underway for the 6.7 release (December 2018 release).

Task Name

Duration 80 days 44 days 2 days 70 days 20 days 10 days

Start

Finish

Gather Requirements Design & Estimate

✓ ✓

Estimate Review and Prioritization

Code Development Functional Testing Preliminary Regression

UAT

5 days

Full Regression Release Planning

30 days

3 days 1 day

MS: Deploy 6.7 to Prod

32

Quarterly Report - Q1 2018